    Doda, November 10: District Development Commissioner (DDC) Harvinder Singh, serving as the Chairman of the District Water and Sanitation Mission (DWSM) under the Jal Jeevan Mission (JJM), recently conducted a comprehensive review of the JJM implementation in the district. The evaluation took place during a meeting of the Jal Shakti Department (JSD) held at the DC office complex.

    During the meeting, the DDC scrutinized the progress of JJM schemes on a project-by-project basis and issued specific directives along with timelines for implementation.

    It was reported that a total of 185 projects, with an estimated cost of Rs 748.31 crore, have been tendered, allocated, and are in the execution phase in the district under JJM. The primary objective is to provide safe drinking water to households through tap water connections.

    CRPF Trooper dies by suicide Near Jawhar Tunnel in Kashmir, Investigation Underway

    Within these 185 JJM schemes, the construction of 372 Slow Sand Filtration plants is planned. Out of these, 207 have been allocated, and work on 133 has commenced on the ground. Additionally, one out of the two sanctioned Rapid Sand Filtration plants has been allotted, and work on three out of the five sanctioned Borewell projects has commenced.

    The Chairman of DWSM (DDC) was apprised that out of the target of 111,216 Functional Household Tap Connections (FHTCs) aimed at providing safe and adequate tap drinking water to all households in the district, 82,452 FHTCs have been completed. In response, the DDC has urged the engineering teams to expedite the completion of an additional 1,000 FHTCs by November 15th, adhering to the previously established timeline.

    Furthermore, the Senior Executive of Jal Shakti Department (SE JSD) has been directed to personally monitor the daily progress of all schemes under the prestigious JJM. The SE is tasked with ensuring that all projects are completed within the specified timeline and in accordance with the highest standards of quality.

    To facilitate this, the SE is required to submit a Program Evaluation and Review Technique (PERT) Chart for all schemes.Addressing the issue of re-tendered Slow Sand Filtration plants, Borewells, and Rapid Sand Filtration plants, the DDC has emphasized the immediate allocation and commencement of work within two days for successfully tendered projects.

    The meeting was attended by Chief Planning Officer (CPO) Doda Suresh Kumar, Senior Executive of Hydraulic Circle Doda Anil Gupta, Executive Engineers, Assistant Executive Engineers, and other relevant officials.

    Review of JJM Implementation in Doda District by DDC:In case of rectification of any error in article , Visit on Correction Policy & Register your Query:

    Asif Iqbal
    Asif Iqbal

    Asif Iqbal is a seasoned news writer with a passion for delivering the latest updates to the public. Currently serving as the senior writer at VoM News, a prominent news outlet known for its comprehensive coverage of diverse topics, Asif has established himself as a reliable source of information. With a keen eye for detail and a knack for storytelling, he consistently provides readers with well-crafted articles that cover a wide range of news categories. His dedication to journalistic integrity and his commitment to staying ahead of the news curve make him an invaluable asset to Vom News, ensuring that readers are always well-informed on the issues that matter most. You can find his work and stay updated on current events by visiting vomnews.in.